  NTT COMMUNICATIONS OPENS DISASTER-RESILIENT OSAKA 5 DATA CENTER

Monday 18/01/2016



-Full-scale disaster-recovery solutions for business continuity planning in Kansai-
 
TOKYO, Jan 18 (Bernama-BUSINESS WIRE) -- NTT Communications Corporation (NTT Com), the ICT solutions and international communications business within the NTT (NYSE: NTT) Group, announced today the immediate launch of the Osaka 5 Data Center in the heart of Osaka, NTT Com’s fifth data center in central Japan’s Kansai Region. The facility offers approximately 3,500 m2 of server room, equivalent to 1,600 racks.
 
Osaka 5 Data Center, which has a dedicated for data-center building comprising 11 floors, is the newest addition to NTT Com’s Nexcenter™ data center service, which combines extensive disaster countermeasures and ideal network environments to enable NTT Com’s customers to accelerate their business development with confidence and efficiency. Please see the attachment for more details.
 
Full-scale disaster-recovery for ensured business continuity planning

Osaka 5 Data Center is fully equipped for disaster recovery to minimize the impact of any envisioned disaster in Osaka, including earthquake, tsunami or flood in the event of a major tremor in the Nankai Trough.
 
In the unlikely event that water were to reach the data center, equipment would continue to operate safely because the electric power equipment, communication facilities, server rooms and other important facilities are located on the second floor or above, over seven meters above ground level. The building’s seismic-isolation device, which lessens the impact of strong shaking by the earthquake, is installed on the post beneath the second floor to ensure that it would work properly if water were to enter the building’s first floor. In addition seismic damper, which suppresses the vertical shaking by the epicentral earthquake, is also installed.
 
Electricity is sourced from separate power substations for extra-highly reliable power supply. The facility is connected directly to a large quakeproof communication cable tunnel that is designed to protect cables from damage due to earthquakes as well as road construction.
 
The Osaka 5 Data Center provides rental office space with back-up power to enable customers to manage BCP solutions easily.
 
Ideal network environment

To ensure that customers have uninterrupted access to a high-quality and low-latency network environment, the Osaka 5 Data Center is connected directly to the NTT Com’s major data center in western Japan, which accommodates Internet exchange (IX), via optical fiber run through cable tunnels.
 
In addition to NTT Com’s high-speed, high-volume Internet backbone and network services, including the Arcstar Universal One virtual private network, customers can use the data center to build seamless ICT environments combining cloud services with data centers worldwide.
 
Also, from this March, a new secure, low-latency data center connection service will enable customers to use NTT Com’s five data centers in Osaka city as if they were one facility. The service will offer up to 10Gbps best-effort circuits or optical fibers.
 
Low-cost operations realized by adopting high-efficiency equipment
 
The Osaka 5 Data Center offers the lower cost services among NTT Com data centers in Osaka. This is possible because of the facility’s exceptional efficiency. To reduce power consumption of cooling, NTT Com has pioneered the adoption of efficient cooling wall which blows cold air in the server room, in addition to using indirect outside air cooling.
 
NTT Com has steadily expanded its data centers and related services, mainly in the Tokyo metropolitan area, to meet the booming demand for data center services in Japan. At the same time, however, customers have been increasingly seeking backup sites in western Japan, which is far enough from Tokyo to serve BCP purposes in the event of a natural disaster. Furthermore, needs for data center services are increasing among financial institutions and manufacturers headquartered in the region.
 
About NTT Communications Corporation
 
NTT Communications provides consultancy, architecture, security and cloud services to optimize the information and communications technology (ICT) environments of enterprises. These offerings are backed by the company’s worldwide infrastructure, including the leading global tier-1 IP network, the Arcstar Universal One™ VPN network reaching 196 countries/regions, and over 140 secure data centers worldwide. NTT Communications’ solutions leverage the global resources of NTT Group companies including Dimension Data, NTT DOCOMO and NTT DATA.
www.ntt.com | Twitter@NTT Com | Facebook@NTT Com | LinkedIn@NTT Com

 
Attachment: Osaka 5 Data Center Specifications
Location
 
 • Nishi-ku, Osaka (4-minute walk from the nearest station)
• 60 minutes by car from Kansai International Airport
 
Building
 
 Structure 11-story steel structure with seismic-isolation construction
 
 Seismic Proofing • Seismic-isolation system decreases seismic shocks by up to 80%
• System to minimize vertical shaking in a locally centered earthquake
• Withstands seismic forces equal to those of Kobe Earthquake or Great East Japan Earthquake
 
 Maximum Load
 
 1,500 kg/m2
 
Power

 
 Power Receiving
 
 • 77,000 V extra-high-voltage power
• Main line and standby power supply system
• Sourced from two different power substations
• Total power: 17MVA (+17MVA standby)
 
Generator

 
 • N+1 redundant configuration
• Power for more than 48 hours without refueling
 UPS
 
 • N+1 redundant configuration
• Battery power for more than 5 minutes
 
Air-conditioning

 
 • Water cooling
• N+1 redundant configuration
• Indirect outside air cooling
• Cooling wall system
 
Fire Protection
 
 • Nitrogen gas fire-extinguishing systems
• High sensitivity smoke detectors
 
Security
 
 • Dedicated system requiring online application for access
• Requires IC card at security gate and biometric authentication
• Surveillance cameras and individually locked racks
• Custom systems for financial institutions, etc. requiring higher security
 

Others Facilities
 
 Rental offices (approx. 420m2) and meeting rooms
 
Connectivity

 
 • Direct connection to disaster-resistant cable tunnel
• Direct connection to NTT Com transmission service node
• Four routes for multi-carriers (NTT Com circuits from two different transformer substations possible)
 
Green Index
 
 PUE: 1.38 (designed value)
 
Certifications (planned)
 
 • ISO27001
• ISO20000
• PCI-DSS
 
Tier level* Tier III
 

* NTT Com assessment based on Uptime Institute’s Tier Classification
 

Contacts
Media Contacts
NTT Communications Corporation
(Mr.) Yuichiro Iwahashi / (Mr.) Hiroshi Seo / (Ms.) Ayu Tsuruta, +81 3 6733-9521
Cloud Services
wg-cl@ntt.com

Source: NTT Communications Corporation
 
View this news release online at:
http://www.businesswire.com/news/home/20160117005124/en
 
--BERNAMA

 
 
 

Copyright © 2024 MREM . All rights reserved.